Coronado Shores Condominium Association #8
1810 Avenida del Mundo
Coronado, CA 92118
EL ENCANTO
Hallway Renovation Project
UPDATE November 28, 2008
For floors 11-16 the work is coming close to being
done! Donate Construction has finished the
stone installation, door veneer and lighting. The
wallpaper is 80% complete as is the painting of the utility doors. We are expecting the new material for the front of
the elevators to be here next week, and once that and the wallpaper is finished the carpet
will be laid. We should have these floors
complete by the week of December 8th.
For floors 6-10, much of the past two weeks have been
dedicated to the stone and door veneer installation. The
walls are 90% ready for wallpaper (a little more plaster and sanding) and the electrical
is ready for light fixture installation. They
will begin applying the veneer around the mirror by the elevator and finishing the
electrical work over the next week.
Floors T-5 have gone through the demo (and dirtiest) phase. The walls still require plaster and sanding, but
the door veneer installation is already at the 2nd floor.
Installing the stone has also begun on the 5th floor.
The Lobby has new soffits and additional lights installed. The Mailroom walls are prepped and primed.
Our staff is continuing to run new RG6 wire through the
soffits and connecting to the 5 phone rooms starting at the top 5 floors.
UPCOMING EVENTS
EL ENCANTO HOLIDAY PARTY FRIDAY DECEMBER 12th
FROM 5:30-7:00
Feel free to call me anytime with questions or comments.
Thank You,
Alan Aegerter
Association Manager
619-437-8151
| 15 OCT |
|

End Hallway Tile |

New Door Venneer |
|
| 01 OCT |
 |
 |
 |
 |
|